Samita Bhujbal
Ext deployment causes server shutdown
9 de Julho de 2013 23:20
Resposta

Samita Bhujbal

Ranking: Youngling

Mensagens: 0

Data de entrada: 5 de Julho de 2011

Mensagens recentes

I am working in liferay 6.1.1. I have created ext for Calendar portlet to add 2 extra values in add event form. It is working fine on local environment.
But when I deployed it to staging server, server gets stopped. What might be the reason behind this???
Apoorva Prakash
RE: Ext deployment causes server shutdown
10 de Julho de 2013 05:30
Resposta

Apoorva Prakash

Ranking: Youngling

Mensagens: 0

Data de entrada: 15 de Junho de 2010

Mensagens recentes

Samita Bhujbal:
I am working in liferay 6.1.1. I have created ext for Calendar portlet to add 2 extra values in add event form. It is working fine on local environment.
But when I deployed it to staging server, server gets stopped. What might be the reason behind this???


Hi Samita,

It will be easier to intercept issue if you can put some log.

Thanks and Regards,
Apoorva Prakash
Samita Bhujbal
RE: Ext deployment causes server shutdown
11 de Julho de 2013 23:08
Resposta

Samita Bhujbal

Ranking: Youngling

Mensagens: 0

Data de entrada: 5 de Julho de 2011

Mensagens recentes

Hey issue was different. Got it resolved now.